How to make line plan for garment production

Line plan:Daily production target plan of multiple styles in order to meet delivery date of each style by keeping in knowledge about line capacity as per construction features and order quantity of each styles.  Line plan is the key aspect in garment planning division. Planning section is making the production out cum plan as per line capacity in order to achieve delivery date. Planner needs to do backward and forward planning based on lead time.Mostly line planning is made after discussion with team of Production and IE.

In order to make target achievable line plan you should have to keep below require data when making a line plan.
1. Order detail sheet
2. No Of Line and there capacity
3. Style SAM as per quality stander
4. Average manpower absenteeism percentage
5. Production lead time of an order
6. Holiday list

See below line plan chart to understand all above requirement sequence wise in order to make a line plan.

1. Order detail sheet:Order Detail sheet is the first requirement for making a line plan in order to take decision about line selection for an order as per there quantity and production lead time considering delivery date.
Order No
Category
Order qty
Delivery date
MARITO
Trouser
6400
31st July
Jet king
Trouser
33000
31st Aug
Merina
Trouser
2336
3rd Aug
Elvis
Trouser
5400
4th Aug
Ertica
Trouser
6000
19th Aug
Stylek
Trouser
3240
28th Aug


2. No Of Line and there capacity: Its very important for a planner to know about No of production line available for total order in hand.Capacity of line is require to set daily production target of an order.Average Line capacity chart can be prepare as below.
Line No.
No. of Operator
Minutes/Day
Line Efficiency
Absenteeism %
Capacity available
(Daily working Hrs. X 60)
Line 1
30
480
40%
10%
5184
Line 2
28
480
50%
10%
6048
Line 3
32
480
55%
10%
7603.2
Line 4
32
480
45%
10%
6220.8
Line 5
25
480
39%
10%
4212
 
3. Style SAM/SMV : Stander allowed minute or stander minute value of  style helps a planner to fix daily target qty of a line by calculating production rate through it.

4. Average manpower absenteeism percentage: Man power absenteeism is common in garment or any other industries.Line capacity can't complete without knowing absenteeism in order to make actual capacity of production line.

5. Production lead time of an order: Production lead time helps to select no of production lines for  style as per there qty to complete production on time.
Order No.
Loaded to Line No.
Order Quantity
Style SMV
Capacity Required (Minutes)
Capacity available per day
Capacity Required (Days)
MARITO
Line-1
6400
28
179200
5184
35
Jet king
Line-2
33000
25
825000
6048
136
Merina
Line-3
2336
20
46720
7603.2
6
Elvis
Line-4
5400
10
54000
6220.8
9
Ertica
Line-5
6000
18
108000
4212
26
Stylek
Line-1
3240
28
90720
5184
18
 

6. Holiday list: List of holiday need to know while making line plan order to extend the date if there any holiday in between.

Style change production lose need to be consider while making a line plan, for example-  If line-1 per day capacity for style is 400pcc. But production starting days (first,second and third day) the output will be in ascending orders like- First day-50pcs, second day-150 pcs, and third day-300pcs after that out cum will be 400pcs/day.














7 comments:

ngocbedt said...

Hi! I would like to have your planning sheet to apply. Can you please share it to me? My email is ngocbedt@gmail.com. Thank you!

Putri Adiratnaa said...

Loan Opportunity Offered By Mr, Benjamin That Save My Family From Financial Bondage {  247officedept@gmail.com  }

Hello Everyone, I am Putri Adiratnaa single mom from Jakarta, I would like to share this great testimony on how I got a loan from Mr, Benjamin, when we were driven out of our home when I couldn't pay my bills anymore, After being scammed by various companies online and denied a loan from my bank and some other credit union I visited. My children were taken by the foster care, I was all alone in the street. The day i shamefully walked into an old school mate who introduced me to Daisy Maureen. At first I told her that I am not ready to take any risk of requesting a loan online anymore, but she assured me that I will receive my loan from them. On a second thought, due to my homelessness I had to take a trial and applied for the loan, luckily for me I received a loan of $80,000.00 from Mr, Benjamin. I'm happy I took the risk and applied for the loan. My kids have been given back to me and now I own a home and a business of my own. All thanks and gratitude goes to  the help of Mr, Benjamin for giving me a meaning to life when i had lost all hope. If you currently seeking for a loan assistance, you can contact them via: {247officedept@gmail.com    WhatsApp +1-989-394-3740.

Unknown said...

I would like to make sewing line plan in which show that how many days will be complete one order and when should be start in line based on shipment date with less holiday.
Kindly guide me in excel sheet with formula..

Narayana Rao K.V.S.S. said...

Machine Work Study in Garment Manufacturing Factories

Unknown said...

V good information

Unknown said...

V nice work need more information

Asraful Haque said...

Very nice

Formal blazer operation break down

Blazer operation break down(OB) : As we know formal jacket is combination of three layer materials( Body fab, Lining, interlining & canv...